City of Cape Town: all solar PV and battery systems need to have a City-approved inverter registered by October

Google+ Pinterest LinkedIn Tumblr +

News Flash

  • City of Cape Town mayoral committee member for energy, Beverley van Reenen, has confirmed that from October 2023, all solar PV and/or battery storage applications at the City of Cape Town will be treated as grid-tied systems.
  • This means that all systems need a City-approved inverter and professional sign-off.
  • Residents without approval face R5000–R7000 fines.

The authorisation process for embedded generation installations applies to small-scale embedded generation (SSEG) systems with a generation capacity smaller than 1 mega-volt ampere (MVA) and embedded generation (EG) systems with a generation capacity of more than 1MVA and less than 100MVA in properties within the City of Cape Town electricity supply area.

Read more on how to apply HERE

Link to the list of approved inverters HERE

Related news: SMA is listed as one of the top three inverter manufacturers in the world 

Author: Bryan Groenendaal

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.