Tanzania Starts Dam Filling For 2.1 GW Julius Nyerere Hydroelectric Power Plant

Google+ Pinterest LinkedIn Tumblr +

Project Details and Scope of Works

  • Employer: Tanzanian Ministry of Energy
  • Contractors: JV Arab Contractors Company and Elsewedy Electric
  • Project location: Stigler’s Gorge Area, the dam is located in the Morogoro area on Rufiji River – Tanzania
  • Completion Period: 62 months including 6 months mobilization

Project Objective

Generating electricity with capacity of 2115MW to satisfy energy needs in Tanzania

Scope of Work

  • Main dam for storage of water to generate hydropower using RCC concrete for main dam with total length 1025m at crest level and 130m dam level.
  • Construction of 4 saddle dams for reservoir impounding of water with length of 1.4km, 7.9km, 4.6km and 2.6km with a maximum height 21.3m, 14m, 12.4m and 5.5m respectively, with a capacity to impound approximately 33 billion m3 of water.
  • Construction of a hydropower plant with a capacity of 2115mw and a substation of 400kv; in addition to 400kv transmission lines to the nearest point of the public network.

Civil works

  • Permanent access roads connecting the site with the existing roads network and length about 21km.
  • Temporary access roads that connect all permanent facilities with length of 59km
  • Main dam of RCC on Rufiji River Power plant with administration building, control building, workshops and stores.
  • Connecting power station 400kv including transmission lines 4 variable height and length dams for water impounding of reservoir Diversion tunnel 660m length (15*17m) and 2 cofferdams.
  • The main spillway is located on the center of the main dam with 7 radial gates and an emergency spillway is located in the first saddle.
  • Permanent concrete bridge on Rufiji River.
  • Integrated residential complex on an area of 19000m including housing and playground, permanent furnished offices; in addition to temporary residential complex, utilities, lighting, drinking water and water treatment.

Main electromechanical works for power house

  • Power plant 2115 -9 vertical Francis turbines, each turbine capacity is 235mw
  • 9 butterfly valves for entrance
  • 9 vertical axis generators
  • Water and sewage cooling systems
  • Ventilation, air-conditioning, firefighting and communication systems
  • Protection, control and monitoring equipment
  • 3 diesel generators for the power plant, dam and spillway

Massive impact

Upon completion, with a total electricity generation capacity of 2,115 megawatts, the project is expected to cut power tariffs which will lead to the reduction of the cost of living for Tanzanians as well as the production cost in industries. The bulk of Tanzania’s current installed capacity sits at around 1600 MW which is largely composed of hydro 566.79 MW (42%), natural gas 607 MW (45%) and liquid fuel 173.40 MW (13%).

Author: Bryan Groenendaal

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.