South Africa: 557MW Thabametsi Coal Power Project Set Aside

  • Major climate impacts and exorbitant costs have sounded the death knell for one of the last new proposed coal-fired power stations in Thabametsi, which is in water-scarce Limpopo, South Africa.

Last week, environmental justice groups Earthlife Africa and groundWork, who have been challenging the Thabametsi power station in court since 2016, secured agreement from both Thabametsi and the state for the environmental authorisation issued for this power plant by the Department of Environment in February 2015 to be set aside. Earthlife and groundWork argued in court papers that former Environment Minister Molewa had disregarded the devastating climate impacts of the 557MW Thabametsi project (originally approved for a capacity of 1200MW).

The setting aside of Thabametsi’s environmental authorisation means that, should it still plan to proceed, it would have to seek a new authorisation from the Environment Department – a major setback for the project.

Last month, South Korea’s state-run Korea Electric Power Corp, KEPCOannounced its withdrawal from its 50% stake in the Thabametsi project. Earlier this week, it was reported that both the Public Investment Corporation and the Industrial Development Corporation (IDC) had withdrawn their financing too, and the Development Bank of Southern Africa was quoted as saying that it was reassessing the project to determine if it was in-line with its policy of a “just transition towards a low carbon economy”. All South Africa’s private banks have already withdrawn their pledged funding for the project.

“In an environment where renewable energy is much cheaper than coal, any new investment in coal power is completely unjustifiable,” says Earthlife Africa director Makoma Lekalakala. “That is over and above the unconscionable health and environmental costs of coal, which are being borne by communities living in all our coal areas in Mpumalanga, Limpopo and KwaZulu-Natal.”

Thomas Mnguni, groundWork community coal campaigner, agrees. “This is a victory for environmental justice, the just transition and open democracy.”

Had it proceeded, Thabametsi would have been one of the most greenhouse gas emission-intensive coal-fired power stations in the world, and would have cost South Africa R12.57 billion in comparison to a least-cost electricity system.

The IDC, which faces criticism of its ongoing investments in fossil fuels,[2] still seemed to suggest in reports that it would consider financing “clean coal” projects. “Clean coal is a myth,” said Nicole Loser, attorney at the Centre for Environmental Rights who has led the legal challenge of Thabametsi. “There is no version of coal-fired power that curbs greenhouse gas emissions, or adequately mitigates all the harms of coal-fired power to the extent it is required. In any event, the additional costs of this technology make already-expensive coal completely uncompetitive with cheaper clean energy sources.” (Download The Myth of Clean Coal).

Author: Bryan Groenendaal

Source: Centre for Environmental Rights

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.