SA Wind Sector: Regulation Still Requires the Minister to Give the Final Nod

  • During President Cyril Ramaphosa’s State of the Nation address in February 2020, he signalled to Section 34 of the Electricity Amendment Act, to enable municipalities in good financial standing to develop their own power generation projects.
  • This has now come to fruition with the Minister of Mineral Resources and Energy, Gwede Mantashe having gazetted amendments to the Electricity Regulations on New Generation Capacity.

“Whilst this amendment to the Regulations paves the way for municipalities, with good financial standing,  to be able to either develop or obtain their own power-generation capacity from Independent Power Producers (IPPs), which will by and large be renewable energy, the Regulation still requires the Minister to give the final nod,” says Ntombifuthi Ntuli, CEO of the South African Wind Energy Association (SAWEA).

SAWEA believes that although the current uptake may be greatly restricted, this decentralized way of procuring power is a step closure to a broader energy transition that the country needs to increase its power generation and the Available Energy Factor (AEF), which will sustain local economic activity.

Speaking specifically in relation to the role of the Wind energy sector, in the distributed generation space, experts show that distributed generation wind energy projects could be viable at a minimum size of 10 MW with a Power Purchase Agreement (PPA) length of 15 to 20 years.

“This works even better if the smaller projects are built alongside other big projects and they source turbines simultaneously, to minimise costs. The opportunity for IPPs to pair up smaller and bigger wind projects, will be easier once the Renewable Energy Independent Power Producer Procurement Programmes (REI4P) gets underway again,” added Ntuli.

There are various ways that IPPs can transact with municipalities with the idea of selling power that will need to be explored.  The first option is for IPPs to be selling directly to municipalities, in which case the consumer could connect directly to the municipality. The second option is that IPPs could be the municipalities’ virtual supplier from another point on the Eskom network.  And thirdly, IPPs could transact inside the municipalities through wheeling to customers that are on the municipal system, where the municipality becomes the carrier and not the direct off-taker. Any of these off-take arrangements could work, particularly if NERSA allows municipalities to establish a wheeling tariff.

“We still have several emerging questions that need to be addressed as the regulatory environment becomes more conducive for municipalities to procure power directly from IPPs, specifically around whether this additional procurement capacity will be derived from the existing Ministerial Determination or if the Minister will issue a separate Determination for Municipalities,” concluded Ntuli.

Author: Bryan Groenendaal

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.