Madagascar: 205MW Sahofika Hydropower BOOT Scheme to get 4 million Euro Loan

Google+ Pinterest LinkedIn Tumblr +

VOITH - Renewable energy for Africa with hydropower

  • The African Development Fund (AFD) has approved a 4.02 million euro loan with a grant component to finance the Government of Madagascar’s 30 million euro equity investment in the Sahofika Hydropower Project.
  • The project entails the construction of a 205MW hydroelectric power plant on a Build-Own-Operate-Transfer basis.
  • This includes the construction and rehabilitation of 110km of access roads and construction of a 75km, 220kV transmission line.

In December 2019, acting as Mandated Lead Arranger, the Bank approved a Partial Risk Guarantee of $100 million towards the Sahofika project to mitigate liquidity risk.

The Bank is also supporting the Power Transmission Network Reinforcement and Interconnection Project, aimed at reinforcing and expanding Madagascar’s transmission network in order to evacuate the additional power generated by this large hydro project.

Additional funding for the project is expected to come from the European Union and the Arab Bank for Economic Development in Africa

Dr Kevin Kariuki, the AfDB’s Vice-President for power, energy, climate change and green growth, stated: “The support to the Sahofika project exemplifies the Bank’s commitment to delivering quality, affordable energy access across the continent for sustainable and inclusive growth, while helping member countries to responsibly harness their vast, yet underdeveloped renewable energy resources.”

He continued: “As the largest hydro power project under development in the country, the Sahofika project will unlock Madagascar’s hydropower potential, and diversify its energy mix in favour of renewable at 90%.”

According to Mohamed Cherif, the Bank’s country manager for Madagascar: “The Sahofika project is a cornerstone of the Bank’s strong support to the power sector in Madagascar. The commissioning of Sahofika would enable national utility (JIRAMA) to save around 100 million euros annually in fuel costs, while phasing out the need for state subsidies.”

The Sahofika project is aligned with the Bank’s New Deal on Energy for Africa, and the Bank’s Climate Change Action Plan, whose collective goals include expanding green energy infrastructure for sustainable and inclusive growth. It is also in line with the Government of Madagascar’s energy policy.

The ADF is the concessional financing window of the Bank Group that provides low-income Regional Member Countries (RMCs) with concessional loans and grants in support of projects that spur poverty reduction.

Once commissioned, the Sahofika project is expected to contribute to the avoidance of 900,000 tons of CO2 equivalent annually.

The Sahofika project is anticipated to generate affordable, clean energy benefitting some eight million people, is located 100km southeast of the capital Antananarivo on the Onive River.

The government has committed to plough back the returns from the project to reduce electricity tariffs for the people of Madagascar.

Author: Nicolette Pombo-van Zyl

This article was originally published on ESI Africa and is republished with permission with minor editorial changes.

 

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.