Hard stop date for REIPPPP Bid Window 5 and Risk Mitigation generation projects may not be hard stop – again

Google+ Pinterest LinkedIn Tumblr +
  • South Africaโ€™s Independent Power Producer Procurement Office (IPPO) and theย Department of Mineral Resources and Energy (DMRE)ย under which it falls, has repeatedly missed their own legal and commercial close deadline set for 12 outstanding projects named as preferred bidders in the country’s Renewable Energy Independent Power Producer Procurement Programme Bid Window 5 (REIPPPP BW5) plus the outstanding projects in the Risk Mitigation procurement programme which includes the threeย controversial Karpowership gas to power floating plants totalling 1220MW. ย 
  • The projects forย REIPPPP BW5 were awarded back in October 2021ย and theย risk mitigation projects were awarded preferred bidder status in March 2021.ย 
  • The IPPO set a hard stop date for 31st December 2023 for both programmes.ย 
  • Yesterday in his weekly press briefing on the status of South Africa’s energy sector,ย Minister of Electricity in The Presidency for electricity,ย Dr Kgosientsho Ramokgopa,ย confirmed that there had been representations from certain bidders asking for an extension and ‘could not sayย with any degree of certainty that government will still stick to that date’. Link to video of full briefing HERE
  • The ongoing babysitting of preferred IPP bidders with suspect BBBEE partners and projects that were clearly not ready for bid or whoseย bid tariffs are clearly not bankable, has caused massive reputational damage to the countryโ€™s once globally respected renewable energy procurement programme. ย Read moreย 

The DMRE along with the IPPO is responsible for energy procurement in the country.ย Since the Independent Power Procurement Office (IPPO) was seconded to the Central Energy Fund in 2017 and then purged in 2019 to fall under the Department of Mineral Resources (DMRE), the ability of the country to procure new generation capacity has declined dramatically.ย Read more

Related news: Preferred bidders must shoulder blame for delay in financial close of REIPPPP Bid Window 5 projectsย 

Mr Gwede Mantashe was appointed Minister of Mineral and Energy Resources inย May 2019. That same year Mantashe was credited for promulgating the countryโ€™sย Integrated Resource Plan (IRP)ย which seeks to procure 35348MW of a mix of generation technologies by 2030. The following year he gazetted a Sector 34 determination to procure 11813MW of power by 2022.

Since Mantasheโ€™s appointment, three energy procurement programmes have been implemented namely; the Risk Mitigation Independent Power Producer Programme (RMIPPPP) which seeks to procure 2000MW of new generation capacity (launched in September 2020), and the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) Bid Window 5 which seeks to procure 2500MW of new generation wind and solar capacity (launched in April 2021). A third procurement programme, REIPPPP Bid Window 6 which seeks to procure 2600MW of solar and wind capacity, was launched inย April this yearย and updated toย procure 4200MW.ย 

In total, 8700MW is to be procured under the three programmes yet to date onlyย 150MWย ย is feeding electrons into the grid at the end of Q4 2023.

IPPO has delivered a knee-jerk reaction by trying to address the skewed outcome of Bid Window 5ย with updated criteria for Bid Window 6ย but theย reputational damage is evident in the response to Bid Window 6 where the number of bidders has dropped by around half compared to Bid Window 5.ย Read more

The outcome of Bid Window 5 has been unprecedented globally in any renewable energy procurement tender so much so that allegations ofย tender rigging have emerged.ย Taking a closer at the outcome there are also several standouts which differ from previous successful bid windows in South Africa:

South Africa is in a massive energy crisis. Rotational load shedding is getting worse and the cost to the economy is a massive R950 million a day. According to a report presented by the University of Capetown, if 5GW of renewable energy was rolled out before 2021, the country would not be experiencing load-shedding. Read more

Author: Bryan Groenendaal

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.