Eskom Takes Regulator to High Court Over Tariff Application

  • Eskom has initiated proceedings in the High Court to review the National Energy Regulator of South Africa (NERSA) decision to reject Eskom’s MYPD 5 application.
  • “Regrettably, this is the only available option to avoid extremely serious and negative consequences for Eskom and by necessary consequence to National Treasury,” said Eskom in a statement. 
  • The urgent High Court review requires NERSA to urgently process the Eskom revenue application for at least one year, as required by law.
  • The proposed timeframe allows for a decision to be made in time for implementation by 1 April 2022.

 As required by law, Eskom submitted its revenue application to NERSA on 2 June 2021. The application is for implementation from 1 April 2022. The revenue application was made in accordance with the prevailing methodology, as approved by NERSA. This methodology remains valid, until replaced by an alternate.

On 30 September 2021, NERSA rejected the Eskom MYPD 5 revenue application and requires Eskom to make a new application based on a methodology yet to be developed. This is impossible both from a legal process and timing point of view. Read more

“It is hoped that NERSA will respond in a manner that allows for the stability of the country’s economy and the electricity industry,” Eskom concluded.

Author: Bryan Groenendaal

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.