Eskom: Medupi’s Unit 3 Design Defects are Repaired

  • Eskom has announced that following a 75-day outage to repair major design defects, Medupi’s Unit 3 has since last week Tuesday, 05 May 2020, reached the full generation capacity of 793 MW.

“Completing the Unit 3 outage within time, demonstrates Team Medupi and its Contractors’ commitment to improving plant performance in terms of availability and reliability. This critical achievement is laudable as its success is dependent on different role players doing their bit to bring workable solutions,” said Jan Oberholzer, Eskom’s Chief Operating Officer.

The major focus of the outage was to implement the technically agreed solutions for the boiler issues that hobbled the performance of the unit; these being the boiler plant modifications of the re-heater spray flow, pulse jet fabric filter plant, gas air heater, milling plant, duct erosion, and dust arrestors.

The Unit is currently undergoing optimisation and performance testing prior to conducting the boiler performance verification tests, which require inspections and equipment tests to be conducted after 2,500 hours of operation in order to verify the success of the modifications.

Eskom is currently implementing similar modifications for which the level of confidence of success is high on Unit 6, which is on an outage, after which we will move to Unit 1, starting mid-May 2020. Unit 4 will also be taken off the grid in July 2020 for similar modifications. Unit 2 will be taken off the grid late August 2020, followed by Unit 5 in November 2020.

Author: Bryan Groenendaal

Source: Eskom

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.