- Following five months of vigorous testing and optimisation, Eskom has announced that Unit 4 of the Kusile Power Station Project was yesterday handed over to the Generation division to formally be part of the Eskom commercial fleet.
- The handover marks another milestone in Eskom’s efforts to stabilise the power system in that it has formally added a much needed 800MW to the country’s power system.
- The unit was connected to the national grid for the first time on 23 December 2021.
“This milestone means the construction of four out of the six generation units have now been completed at the Kusile Power Station project. The Kusile project team and Eskom are working tirelessly to complete the rest of the project without any further delays as the country needs every megawatt of power it can get,” said Bheki Nxumalo, the Eskom Group Executive for Capital Projects. Nxumalo further appreciates Eskom Guardians and Contractors, who worked tirelessly to deliver the unit to its successful commercial operation.
Related news: Kusile Design Modifications Progress and Problems
The unit has undergone a series of tests while intermittently supplying electricity over the past five months. Since synchronization in December 2021, the unit has performed to expectation, intermittently sending up to 720MW and contributing to reducing the implementation of loadshedding.
Related news: Eskom pins hopes on Kusile and Medupi power stations to ease loadshedding
At completion, the station will consist of six units, and will produce a maximum 4 800MW. Construction and commissioning activities on the remaining Kusile Units 5 and 6 continue to progress according to plan. Situated near eMalahleni in Mpumalanga, Kusile is South Africa’s largest construction project and will be the world’s fourth largest coal plant at completion. Read more
“Eskom is fitting wet flue gas desulphurisation (WFGD) to the Kusile plant as an atmospheric emission abatement technology, in line with current international practice, to ensure compliance with air quality standards, making it more environmentally friendly,” the company said.
Kusile is the first power station in South Africa and Africa to use WFGD technology. WFGD is the state-of-the-art technology used to remove oxides of sulphur (SOx), for example, sulphur dioxide (SO2), in the emissions of power plants that burn coal or oil.
Author: Bryan Groenendaal