Zimbabwe Pins Hopes on 500MW From Zambia and Mozambique

Google+ Pinterest LinkedIn Tumblr +
  • Efforts to reduce load shedding considerably are bearing fruit with Zimbabwe soon to get up to 500MW of electricity from Zambia and Mozambique, while Hwange Power Station’s Unit 7 should be feeding 300MW into the grid before month end, Zesa Holdings executive chairman Dr Sydney Gata said in an exclusive interview with Zimbabwe’s biggest dailt newspaper, The Herald, on Friday. 

Owing to low water levels at Lake Kariba and aged thermal power stations, the small ones with equipment now 72 years old and even Hwange more than 34 years old, Zimbabwe is battling massive electricity outages, with some people saying they only have power between 10pm to 5am.

Dr Gata said Zimbabwe has been busy working on measures to address the electricity challenges, and a huge difference in terms of the load shedding schedule, would soon be noted across the country. “As for the current load shedding, there is relief that is coming. We ran around and apart from getting a bit more from Kariba, we will be getting a bit more from Zambia and Mozambique,” said Dr Gata.

Related news: Zimbabwe has no foreign currency to pay upfront for electricity imports

“From Zambia we are getting 100MW and they are looking for another 50MW for us and there is also a member of the Intensive Energy Users Group who is also looking for another 100MW. So we may get as much as 250MW from Zambia. From Mozambique I was there recently and we agreed that they will run around and increase from the 60MW they have been giving us, to 100MW immediately, and there is another 150MW which could be coming from Monday next week. So Mozambique should give us 250MW maximum.”

Related news: Zimbabwe’s energy sector hits rock bottom as Kariba Dam and foreign currency dry up

More electricity is expected to come from Hwange’s Unit 7, which is expected to start feeding electricity into the grid before month end. If all goes according to plan, Unit 7 should be connected to the grid a few days before Christmas, said Dr Gata. “The unit itself, in terms of operating, is actually ready to generate. However, there was a delay in equipment required to connect it to the grid,” he said.

Unit 7 has capacity to generate 300MW while on completion in the first quarter of next year, Unit 8 will also add another 300MW to the main grid. For Unit 7, besides the parts, there was a delay in the arrival of engineers from a Chinese firm. But the panels and engineers are now on site and staff are “working frantically” to get Unit 7 onto the grid.

“So far we expect that it could be around the 20th of this month. It could be later, it could be earlier, but thereabout and surely by Christmas, Unit 7 should be in service, barring unforeseen situations,” said Dr Gata.

Source: The Herald

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.