  • Terabase Energy, developer of Terafab, an automated utility-scale solar installation platform, announced it has successfully completed its first commercial installation.
  • The companyโ€™s โ€œfield factoryโ€ installed 17 MW of a 225 MW solar project in Arizona in development by Leeward Renewable Energy and engineering and construction contractor RES.

The Terafab system makes use of digital twins, logistics software, an on-site digital command center, a field-deployed automated assembly line, and installation rovers that can operate 24/7.

In the Arizona project, Terabase said its labor productivity improved 25% when compared with manual installation.

โ€œ[The project] demonstrates that Terabaseโ€™s technology can drive substantial progress in solar construction safety, quality, cost, and schedule,โ€ said Will Schultek, vice president of construction, RES.

The installation system cuts the amount of labor needed on-site and improves working conditions for laborers. Workers are housed in shaded and cooled conditions, allowing for system operation and installation in harsh desert environments.

Image: Terabase Energy

Reducing labor requirements to install utility-scale solar projects may prove useful for accelerating the energy transition. The Solar Energy Industries Association (SEIA) projects a demand of 800,000 new solar workers by 2030 to build the projects the United States needs to be on pace with its decarbonization plan. However, 44% of solar industryย employers reportย it is โ€œvery difficultโ€ to find qualified applicants, said the Interstate Renewable Energy Council (IREC).

Terabaseโ€™s field factory also enabled a 100% return on solar panel packaging for reuse by the manufacturer.

Leeward Renewable Energy executive vice president of project execution Sam Mangrum said the benefits demonstrated in the project underscore the โ€œtransformative potential of automationโ€ in solar.

โ€œThis milestone marks a pivotal moment in our mission to accelerate solar plant deployment to meet the terawatt scale demands of the future,โ€ said Matt Campbell, chief executive officer at Terabase Energy. โ€œFurthermore, the Terafab system was deployed alongside our Construct digital twin software for managing and monitoring solar power plant construction.โ€

Author: Ryan Kennedy

This article was originally published in pv magazine USA and is republished with permission.

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.