- Civil society organisations have welcomed a ruling by the Supreme Court of Appeal, that has denied state-owned enterprise, Eskom, authorisation to build a 3000MW gas-to-power plant in Richards Bay.
The SCA overturned the decision of the Pretoria High Court, which upheld an Environmental Authorisation granted to Eskom by the Department of Forestry Fisheries and the Environment (DFFE), despite acknowledging deep flaws in the public participation process.
South Durban Community Environmental Alliance (SDCEA) and groundWork, are hailing the judgement an outright victory for the affected communities of Richard’s Bay, who were not adequately consulted about the project.
SDCEA and groundWork argued that the Environmental Impact Assessment upon which the Environmental Authorisation was granted, was flawed, not only for failing to conduct consultation in the language of local residents, but also in that it did not consider the climate change impacts of the full lifecycle of the gas-to-power plant, or whether renewable energy options could achieve the same energy objectives. The proposed gas-to-power plant was set to be fuelled by gas via a pipeline installed from the Richards Bay Port with the aim to supply up to 3,000MW of energy for a mid-merit facility. The source of the gas was unclear.
In August 2024 the South Durban Community Environmental Alliance (SDCEA) and groundWork, supported by Natural Justice, represented by environmental law firm, Cullinan & Associates and a team of advocates, took the matter to the SCA in Bloemfontein to challenge a Pretoria High Court judgment that had previously declined to set aside the environmental authorisation granted to Eskom for the gas power plant.
In the SCA judgment shared, the court confirmed that public participation is pivotal to the fulfilment of the right to an environment that is not harmful to the health and well-being. To be effective, public consultation must be conducted in good faith, through culturally appropriate measures and procedures. Eskom and its environmental consultants, Savannah Environmental, did not do so.
The SCA also confirmed that renewable energy alternatives should have been considered, and that the cumulative impacts associated with the extraction and transportation of gas should have been part of the assessment. The Minister had also failed to consider that the government had already determined that any gas power should be provided by Independent Power Producers, not Eskom.
As a result, the SCA crafted a remedy that would enable members of the public to participate meaningfully in any application process, which necessitates a fresh application by Eskom for authorisation once the required public participation has taken place and once the various requirements which had not been complied with, have been attended to. The environmental authorisation was therefore set aside. “The effect of this order is that the authorisation is a nullity”, reads the judgment.
This matter was first heard in the Pretoria High Court in August 2022 and was considered a landmark case, as it was the first time that a gas-to-power plant had been challenged in a court in South Africa.
At the time, CSO’s raised concerns about the inadequate assessment of the climate change impacts of the project and called for the environmental authorisation to be declared unlawful and set aside, based on inadequacies within the Environmental Impact Assessment (EIA) and a flawed public participation process. None of the communications during the public participation process had been conducted in the home language of the majority of people in the area (isiZulu).
In October 2022, the Pretoria High Court (despite finding the Applicants’ 5th review ground to have merit – impliedly justifying a review of the impugned decisions) dismissed the review application and refused to set the impugned decisions aside.
But, it did grant ancillary orders to the effect that the decision to grant the environmental authorisation should be published in isiZulu and the communications in future EIAs for the gas terminal and pipeline should also be in isiZulu. This unfortunately meant that the environmental authorisation remained valid.
CSO’s appealed in the SCA and the appeal hearing took place in Bloemfontein on Friday 30 August 2024, and today, a year later, the courts have agreed with CSOs.
Desmond Desmond D’sa from SDCEA said: “The case that was won at the Appeal court is a vindication of justice for people and the environment. Eskom for too long, as a state parastatal has gotten away with injustices and people that have lived alongside its facilities will suffer from the high costs of the tariffs, high levels of pollution. We welcome the judgment from the Appeal court and we certainly believe that Eskom must now move away from fossil fuels to a just energy transition”.
Author: Bryan Groenendaal










3 Comments
The (unintended?) consequence of this decision being to further prolong the dominance of coal in our energy mix.
Our courts have since become a useful instrument to block development projects. We are well-aware of our energy supply challenges and that this kind of behaviors that in some way are developmental obstacles aren’t what we need, currently. Whoever is funding these NGO’s has successfully found an effective tool to bring down our country to its knees.
This is another way of ensuring that coal tracks that are destroying our roads ,polluting air around richards bay, causing havoc ,killing people are operational forever . We need an alternative to the electricity crisis . Only God knows the 😭