- Stage 4 loadshedding will be implemented in South Africa from 16:00 Sunday until 05:00 on Monday.
- Thereafter, Stage 2 loadshedding will be implemented from 05:00 until 16:00. This pattern will be implemented daily until further notice.ย
Breakdowns have reduced to 15 798MW of generating capacity while the generating capacity out of service for planned maintenance is 3 099MW.
Over the past 24 hours, a generating unit each at Grootvlei, Kendal, Kriel, Majuba and Medupi power stations was returned to service.
The delay in returning to service a generating unit at Kendal and two generating units at Tutuka power stations is contributing to the current capacity constraints.