- Eskom reports that due to the loss of three generating units and the delay in returning a further three generating units to service, Stage 3 loadshedding will be implemented from 16:00 today until 05:00 on Wednesday.
- Thereafter, Stage 2 loadshedding will be implemented until 16:00.
- This alternating pattern of Stage 2 loadshedding from 05:00 until 16:00 and Stage 3 loadshedding from 16:00 until 05:00 will be repeated daily until further notice.
Unplanned outages account for 15 611MW of generating capacity, while the capacity out of service for planned maintenance is 5 487MW.
Source: Eskom