Stage 3 blackouts reported in South Africa

Google+ Pinterest LinkedIn Tumblr +
  • Eskom reports that due to the loss of three generating units and the delay in returning a further three generating units to service, Stage 3 loadshedding will be implemented from 16:00 today until 05:00 on Wednesday.
  • Thereafter, Stage 2 loadshedding will be implemented until 16:00.
  • This alternating pattern of Stage 2 loadshedding from 05:00 until 16:00 and Stage 3 loadshedding from 16:00 until 05:00 will be repeated daily until further notice.

Unplanned outages account for 15 611MW of generating capacity, while the capacity out of service for planned maintenance is 5 487MW.

Source: Eskom

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.