  • Stage 1 loadshedding (blackouts) will be implemented from 16:00 today until 05:00 on Monday.
  • Thereafter, Stage 2 loadshedding will be implemented from 05:00 until 16:00 on Monday followed by Stage 3 loadshedding until 05:00 on Tuesday.
  • On Tuesday and Wednesday Stage 1 loadshedding will be implemented from 05:00 until 16:00 and Stage 2 loadshedding will be implemented from 16:00 until 05:00. 

Breakdowns have increased to 15 777MW of generating capacity while 6 122MW of generating capacity is out of service for planned maintenance.

Over the past 24 hours three generation units were returned to service at Duvha, Kendal and Kriel power stations.

In the same period, a generating unit at Kendal, Kriel and Majuba power stations were taken offline for repairs. The delays in returning units to service at Duvha, Hendrina, Kriel, Majuba, Medupi and Tutuka power stations continue.

Author: Bryan Groenendaal

Source: Eskom 

 

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.