South Africa: Civil Society in Court to Challenge Gas Power Plant in Richards Bay

Google+ Pinterest LinkedIn Tumblr +
  • The South Durban Community Environmental Alliance (SDCEA) and groundWork will be in the Pretoria High Court next week to ask the court to set aside the environmental authorisation granted to Eskom for the construction of a combined cycle power plant in Richards Bay.
  • This landmark litigation marks the first time that a gas-to-power plant has been challenged in a court in South Africa.

SDCEA and groundWork are supported by Natural Justice and Green Connection, and represented by the law firm, Cullinan & Associates.

Eskom Holdings SOC, a state-owned enterprise, was granted environmental authorisation in December 2019, although construction on the project has not yet begun. The gas-to-power plant will be fuelled by gas via a pipeline that will be installed from the Richards Bay Port and will supply up to 3000MW of energy.

Grounds for review

In their court papers, SDCEA and groundWork have called for the environmental authorisation to be declared unlawful and set aside based on inadequacies within the Environmental Impact Assessment (EIA) and due to the public participation process that was undertaken being flawed.

In the Earthlife Africa judgment handed down in 2017, the Constitutional Court stated that climate change impacts must be assessed before issuing an environmental authorisation for a proposed project. In the current case, SDCEA and groundWork argue that there was an inadequate assessment of the climate change impacts of the project. Evidence shows that a gas power plant, such as the proposed plant, emits as many greenhouse gasses as other fossil fuels, like coal, during the entire life-cycle of a project.

The EIA failed to provide a sufficient analysis of the need and desirability of the gas-to-power plant. In fact, the applicants filed an expert report which found that combined cycle capacity is not needed in the next decade, and that 3000MW of combined cycle capacity would not be needed until 2041 at the earliest. Other studies have confirmed this *. Developing this project will lock South Africa into long-term fuel cost commitments, and this is neither needed nor desirable. The court papers also argue that the decision makers should have considered that renewable energy is an alternative fuel source.

The gas-to-power plant will be linked via a pipeline from the Richards Bay Port. The impact of this was not considered in the EIA, and hence it failed to consider the cumulative impacts of the pipeline, as well as the many other gas projects proposed in Richards Bay.

The public participation process for this development was flawed, as many communities were excluded from the public participation process. These included traditional communities in surrounding rural areas. The information about the project was also advertised exclusively in English despite the EIA Report itself recognising that 79% of the population of uMhlathuze Municipality, where Richards Bay is situated, speak isiZulu.

The case will be heard in the Pretoria High Court on 2 and 3 August 2022.

Author: Bryan Groenendaal

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.