  • Eskom has announced that due to a severely constrained generation system as a result of multiple unit breakdowns, it has become necessary to implement Stage 2 loadshedding from 12:00 to 22:00 today.
  • Ten generation units at seven power stations suffered breakdowns in the last 48 hours.
  • As the aged generation infrastructure is unreliable and volatile, this constrained power system is expected to persist for the rest of the week.

A generator each broke down at Arnot, Medupi, Lethabo, Matla power stations, while two units each at Majuba, Camden and Tutuka power stations also broke down. This, together with the need to conserve emergency generation reserves, necessitates that loadshedding be implemented in order to protect the integrity of the system.

Unplanned breakdowns stand at 11 665MW of capacity, adding to the 4 558MW currently out on planned maintenance.

Any further deterioration in the generation performance may necessitate the escalation of loadshedding at short notice.

Author: GBA News Desk

Source: Eskom

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.