SA Energy Crisis Update: Pattern of Stage 3 and 4 Repeated Until Further Notice

Google+ Pinterest LinkedIn Tumblr +
  • Stage 4 loadshedding will be implemented from 16:00 today until 05:00 on Tuesday morning.
  • Thereafter, loadshedding will be reduced to Stage 3 until 16:00.
  • Stage 4 will then be implemented from 16:00 until 05:00 on Wednesday morning.
  • This pattern of Stage 3 and 4 will be repeated until further notice.

Over the past 24 hours, a generating unit each at Camden, Duvha, Majuba and two units at Kriel Power Station suffered breakdowns and were taken offline for repairs. The return to service of a generating unit each at Hendrina, Medupi and Tutuka power stations was delayed. In addition, the repairs to the damaged towers from Cahora Bassa is taking longer than anticipated.

A generating unit each at Duvha and Kriel power stations were returned to service during this period.

Breakdowns currently amount to 17 340MW of generating capacity while 5 654MW of generating capacity is out of service for planned maintenance.

Source: Eskomย 

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.