- Loadshedding will continue to be suspended until 05:00 on Monday.
- Thereafter, Stage 1 loadshedding will be implemented from 05:00 until 16:00 on Monday.
- Stage 2 loadshedding will be implemented from 16:00 on Monday until 05:00 on Tuesday.
- Loadshedding will be again suspended from 05:00 until 16:00 on Tuesday.
- Then Stage 2 loadshedding will be implemented from 16:00 on Tuesday until 16:00 on Wednesday.
- Eskom will publish a further update as soon as any significant changes occur.
Breakdowns are currently at 15 645MW of generating capacity while 4 942MW of generating capacity is out of service for planned maintenance.
During the last 24 hours a generating unit at Duvha Power Station was taken offline for repairs. The delays in returning units to service at Matla, Tutuka and Medupi power stations continues.
Source: Eskom