The risk of both nuclear reactors at Eskom’s Koeberg nuclear power station in the Western Cape Province of South Africa being shut down simultaneously for life-extension continues to increase.

Keith Featherstone, Eskom’s chief nuclear officer, confirmed on 19 October 2023 that there will be a further approximately 10-day delay in the return to commercial operation of the 970 MW Unit 1 at Koeberg, which is currently undergoing life-extension work.

Eskom has previously extended the expected date for the return to service of Unit 1 several times from the initial indicated completion date of mid-June 2023. The last scheduled date for the return to service of Unit 1 was 3 November 2023.

Unit 1 at Koeberg is now expected to be synchronised to the grid by 30 October 2023, and to return to commercial operation at full output by 13 November 2023, after increasing the output through different power levels and performing the associated commissioning tests.

The shut-down of the 970 MW Unit 2 at Koeberg will therefore also be delayed, if necessary, until after the commissioning of Unit 1 is complete, and stable commercial operation is achieved. This is to avoid a situation where both Units 1 and 2 are down at the same time.

Koeberg nuclear power station is currently the only one on the entire African continent. It is located 30 km north of Cape Town, near Melkbosstrand on the west coast of South Africa.Two generation units make up the 1860MW capacity. Image credit: Bjorn Rudner

Unit 2 will be shut down for refuelling, maintenance and replacement of its three steam generators, in a similar operation to that of the 11-month outage of Unit 1 that commenced in mid-December 2022. Eskom hopes the lessons learned on Unit 1 will result in a shorter outage for Unit 2.

After the return to service on 13 November 2023, Unit 1 is scheduled for a further 200-day shutdown commencing on 21 July 2024, the same day that the current operating licence of the Koeberg nuclear power station expires.

This would appear to indicate that the National Nuclear Regulator (NNR) may not be in a position to grant an extension of the Koeberg operating licence when the current Koeberg operating licence expires on 21 July 2024.

Eskom has indicated that even after the 9-month outage of Unit 1 in 2023, it still needs to conduct a series of overpressure tests on the concrete containment building that covers the nuclear reactor. The containment building is an essential safety structure intended to contain nuclear radiation in the event of an accident or melt-down of the nuclear reactor.

It has previously been reported that in the past 40 years of operation, significant cracks have appeared in the concrete of the containment buildings at Koeberg. The buildings now need to be properly overpressure tested to ensure that radiation cannot leak out in the event of an accident, and that any such cracks and leakages are identified and repaired.

In the meantime, Eskom has applied to the NNR for separate expiry dates in the Koeberg licence for Unit 1 and Unit 2, based on the rationale that Unit 2 was commissioned about 18 months after Unit 1. Eskom is still awaiting a decision from the NNR in this regard.

If the NNR decision in respect of a separate extended expiry date in the Koeberg operating licence for Unit 2 is not granted, then it is possible that both Unit 1 and Unit 2 may have to shut down on 21 July 2024.

Author: Chris Yelland, EE Business Intelligence

Chris is an internationally respected energy analyst, consultant and electrical engineer. He is considered an expert on the South African energy market.

This article was orginally published by EE Business Intelligence and republished with permsission.

Disclaimer: The articles and videos expressed in this publication are those of the authors. They do not purport to reflect the opinions or views of Green Building Africa, our staff or our advertisers. The designations employed in this publication and the presentation of material therein do not imply the expression of any opinion whatsoever on the part Green Building Africa concerning the legal status of any country, area or territory or of its authorities.

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.