  • Steag Solar Energy Solutions, a unit of Germany-based power company Steag, announced it will build three PV power plants with a combined capacity of 244 MW in the Italian southern region of Apulia for an unspecified investor.

The three unsubsidized projects will be located within a radius of 20 km in the province of Foggia and will integrate the production of olives and energy on the same field in order to save space and generate mutual benefit for both.

“The trackers of the photovoltaic system will be interspersed with rows of olive groves,” Steag’s press officer, Daniel Mühlenfeld, told pv magazine. “The distance between the rows of the olive grove and the photovoltaic system has been specifically designed both to avoid shadowing and allow the passage of the automatic machinery necessary for the cultivation of the olive trees.”

The basic design of the three plants.Image: Steag

The main challenge in building these kinds of agrivoltaic projects, according to Mühlenfeld, will be maintaining the maximum efficiency of both production systems keeping CAPEX and OPEX in mind. “There are additional costs to integrate the PV into olive groves, but there are also additional revenues as the intensive olive plant for itself is a business case,” he further explained.

Except for the trackers that need to be higher than usual, no special components are being used for the plants. “The concept and its design are the main special component,” Mühlenfeld added. The project has been designed “to optimize power yield and agricultural yield, but the power yield only is already enough for the bankability of the projects.”

Final approval for the three plants is expected to be obtained between the third or fourth quarter of this year. Construction is scheduled to start at the end of 2021.

Steag is currently also developing what could become Italy’s largest solar plant — a 700 MW facility planned in unspecified areas on the southern island of Sicily. German independent investment and asset manager KGAL is partnering with Steag on the project. “The plant is located in various places in the provinces of Palermo and Trapani,” a Steag spokesperson told pv magazine in February. “The construction will start in the third quarter of 2021 and the plant will be grid-connected during autumn 2022.

Author: Emiliano Bellini

This article was originally published in pv magazine and is republished with permission.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.