Eskom Takes One Unit Offline at Koeberg Nuclear Plant for Refuelling and Maintenance

  • South Africa’s state owned energy utility, Eskom, has announced that Unit 2 of the Koeberg Nuclear Power Station will on Monday 17 January 2022 be taken offline for a regular refuelling and maintenance outage that is scheduled for five months.
  • This will be the 25th refuelling outage on Unit 2 since commissioning and will also see the replacement of the unit’s three steam generators.
  • During this outage the reactor pressure vessel head, which houses the nuclear fuel while the station is in operation, will also be replaced.

The Koeberg Unit 1 outage, of a similar duration, will follow later in the year during which the Unit 1 steam generators will also be replaced; its reactor pressure vessel head was replaced several years ago. The extended unavailability of the units due to the planned long outages does mean the electricity supply system may be under additional strain during the coming year.

“This is going to be a long, but needed outage – the first of its kind for Koeberg. Our staff are prepared and committed to make history by ensuring success of this project,” said Riedewaan Bakardien, Eskom’s Chief Nuclear Officer. “Nuclear safety is the paramount factor. We will progress the outage work diligently, making sure nuclear safety and safety of plant, personnel and public is top of mind.”

Related news: Life-Extension of Koeberg Nuclear Power Station Poses Significant Risks

Unlike other types of power stations, where fuel can be added to continue generating power, the fuel at a nuclear power station is sealed inside a reactor vessel, which is opened for refuelling every 15 to 18 months. This is also a time when the station will perform certain required inspections on equipment and perform more intrusive maintenance that cannot be performed when the unit is online. When Koeberg Unit 2 shuts down on Monday 17 January 2022, it will have been online, safely generating electricity, for 452 days without any interruption since its last refuelling outage, which was completed in October 2020. The rigorous maintenance, inspection and testing programmes are some of the critical activities that ensures that the plant remains safe and able to deliver this reliable level of performance.

Related news: Eskom: Eskom Connects Unit 4 (800MW) at Kusile Power Station to the Grid

Koeberg Nuclear Power Station recently completed a key industry periodic nuclear safety review, and the station was confirmed by independent industry reviewers to be performing strongly in terms of safety and reliability. The National Nuclear Regulator (NNR) also routinely performs crucial regulatory reviews and monitoring aimed at ensuring that the station remains safe and meets all regulatory requirements.

Author: Bryan Groenendaal

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.