Eskom reports breakdowns of eight generating units in one night

Google+ Pinterest LinkedIn Tumblr +

News Flash

  • South Africa’s state owned energy utility, Eskom, reports that due to the breakdowns of eight generating units on Tuesday evening, Stage 4 loadshedding will be implemented from 16:00 today until 05:00 on Thursday.
  • Thereafter, varying stages of loadshedding will be implemented until Saturday evening.

Breakdowns have increased to 19 127MW of generating capacity while the generating capacity out of service for planned maintenance is 2 313MW.

Since Tuesday evening, two generating units at Grootvlei Power Station were returned to service.

The delay in returning to service a generating unit each at Kendal, Kriel, Matla, and two generating units at Tutuka power stations is contributing to the current capacity constraints.

Author: Bryan Groenendaal

Source: Eskom

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.