  • Over the past 24 hours, Eskom has returned to service five generating units which will allow the emergency reserves to be adequately replenished by Tuesday morning.
  • This will enable the reduction of loadshedding (blackouts) to Stage 3 from 05:00 on Tuesday until 16:00. Stage 4 loadshedding will then be implemented from 16:00 on Tuesday until 05:00 on Wednesday.
  • This alternating pattern of Stage 3 loadshedding from 05:00 to 16:00 and Stage 4 loadshedding from 16:00 to 05:00 will be repeated daily until further notice.
  • Eskom will closely monitor the power system and communicate any changes to loadshedding should it be required.

Unplanned outages have reduced to 14 579MW of generating capacity, while the capacity out of service for planned maintenance is at 7 316MW.

Eskom Power Station General Managers and their teams continue to work diligently to ensure that additional generating units are brought back to service. A total of 2 150MW of generating capacity is planned to be returned to service by Wednesday.

Source: Eskom

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.