  • South Africa’s state owned energy utiltiy, Eskom, is piloting a national demand response programme in the small commercial and residential sector in response to the electricity crisis facing South Africa at present.
  • This programme is an expansion of the successful industrial Demand Response Programme, which has been operational for over 10 years.

The objective of the pilot is to test, among others, the appropriateness of technologies, market uptake, and the implementation and participation in this sector. The pilot will enable Eskom to evaluate projects on an ongoing basis until the threshold of 50 MW has been reached.

What is offered?

Qualifying aggregated load providers (ALPs) that meet the demand response criteria will be compensated to reduce aggregated electricity demand when dispatched via Eskom’s system operator.

Key features

  • The ALP needs to be the facilitator of the load to be controlled, measured and dispatched.
  • Minimum load entry level of 1 MW up to 5 MW per submission.
  • The ALP must be registered as an Eskom vendor to participate on the Demand Response Programme.
  • A performance contract will be put in place with the ALP for a period of up to three years.
  • The ALP is scheduled on a day-ahead basis and dispatched on the day, with a 30-minute notification period.
  • The ALP must reduce load on instruction for a minimum of one hour with a maximum of two events per day (maximum 500 hours per annum).
  • The 30-minute interval remote metering is a prerequisite.
  • The ALP will receive an energy payment for verified load reduced.

Step 1: Complete the application form and email to DRPilot@eskom.co.za

Step 2: Your application will be evaluated.

Step 3: Sign a standard legal agreement with Eskom and register as an Eskom vendor if your application is approved.