  • Government’s conduct over the last century and more has led to the situation South Africa finds itself in today as regards the provision of electricity.
  • Tracing a series of legislative and regulatory interventions in the electricity market, we can see how this came to be. 

In the 1890s, companies like Victoria Falls Power (VFP) generated electricity for the Witwatersrand. Transvaal’s 1910 Power Act stated VFP could be expropriated after 35 years.

The 1922 Electricity Act established the Electricity Supply Commission (Escom). Escom built generating stations for the Eastern Transvaal, Natal and Cape peninsula.

VFP, the major Transvaal supplier, applied to erect a large power station at Witbank. Escom objected because VFP sold power at a profit to benefit shareholders, whereas Escom was required merely to cover its costs. It was agreed Escom would finance and own the plant, but VFP would design, build and operate it and transmit surplus power to its grid.

In 1932 Escom was licensed to establish Klip Ppower Sstation. Escom provided the capital and ceded the licences to VFP, who built and operated it.

In 1938, Escom financed Vaal Power Station and VFP built and ran it to feed into Escom’s and VFP’s grids.

Sir Ernest Oppenheimer urged Escom to expropriate VFP. In 1948, Escom purchased VFP’s power stations and plant.

In 1962, a commission of inquiry recommended that municipalities should not expand their generating capacity, but merely distribute Escom power to consumers. Johannesburg’s application to build a new power station was refused.

In the 1970s, Escom extended its transmission lines, resulting in a national grid. Legislation allowed Escom to use tariffs to build up capital.

The Trade and Industries Board investigated electricity supply. Escom contended to the board that it had to keep building power stations to prevent shortages.

Escom over-estimated future demand and began building power stations, leading to excess capacity, yet supply interruptions were common.

In 1983, the De Villiers Commission recommended that Escom should run on business principles and recover five percent more revenue than its expenditure.

The 1987 Eskom Act scrapped the no-profit principle and Escom was renamed Eskom.

In 1987, only 40 percent of people had electricity. In 1993, Eskom and municipalities made 300,000 new electrifications, two-thirds by Eskom; in 1995, 450,000 new connections; and, in 1997, half a million.

In 1998, the government’s energy -policy White Paper observed that Eskom had a de facto monopoly on constructing generation capacity, and, by 1980, had invested in expensive over-capacity with customers bearing the costs. Competition would apply downward pressure on electricity prices.

Government would, over time, consider encouraging private-sector participation in generation, permitting open transmission-system access and letting customers choose electricity suppliers.

Independent Power Producers (IPPs) would be allowed. But fundamental market restructuring would be deferred and developments in other countries would be studied.

Eskom would, in the long term, be restructured into separate generation and transmission companies. Its power stations would be allocated to different companies to introduce generation competition, stated the White Paper.

In 2000, government announced it intended to privatise state-owned companies. This was shelved in 2004. Eskom would remain state-owned to implement the national socio-economic programme, with IPPs merely augmenting supply.

Eskom told the government in 1999 there would be electricity shortages in 2007 unless there was urgent large investment in new power stations, which some privatisation would have achieved. The government failed to finance new build, and did not allow generation competition.

In 2007, power supply fell behind demand for some months. Eskom introduced widespread rolling blackouts (loadshedding).

Because Eskom owns the transmission system, IPPs have had to sell power they generate to Eskom at a price determined by government. Price control undermines market competition.

To overcome this, in 2012, the government introduced a bill to create an Independent System and Market Operator to purchase electricity from producers and onsell it to distributors at a wholesale tariff. The bill went to second reading but was withdrawn.

Loadshedding was reinstituted in 2014 and 2019.

The Madras High Court in India has ruled that lack of electricity affects education and health and causes economic disparity, and denial of access to electricity should be regarded as a violation of human rights.

Eskom’s supply interruptions impair municipalities’ ability to carry out their constitutional objects of ensuring sustainable provision of services and promoting socio- economic development.

Soweto’s debts to Eskom have been forgiven, although they equal the Eskom debts of all other municipalities combined and have already been scrapped twice. Power supply to Soweto has not been cut off, whereas poor rural municipalities are cut off regularly. This violates the principle of the Rule of Law that laws should apply equally.

The 2006 Electricity Regulation Act is impartial about who should produce new generation capacity. Its 2011 Regulations, however, state that the Minister may determine that the producer of new capacity should be “Eskom as part of its services as the national electricity producer”. This, too, violates the principle that laws should apply equally.

The Constitution gives citizens the right to choose their trade. This is consistent with a competitive regime in matters of trade as being in the public welfare, the Constitutional Court has held.

The Companies Act stipulates that a company must not carry on business recklessly. A company is reckless if it fails to heed standards of diligent business people or take reasonable measures to prevent foreseeable harm, say the courts.

Eskom is a company. It has recklessly contributed to Kusile and Medupe’s delays and cost overruns by reportedly not carrying out sufficient scoping or risk management and appointing diverse subcontractors and managing them itself rather than appointing the usual single head contractor to procure and manage subcontractors.

Eskom is also an organ of state, say the courts. The Constitution requires organs of state to promote economic and efficient use of resources. Government’s conduct as regards electricity policy over more than a century does not inspire confidence in such economic and efficient use of resources. Instead, it has sabotaged South Africa’s future, and this can only be reversed by finally allowing competition and private enterprise in the electricity market.

Author: Gary Moore,

Gary is a practising attorney for 30 years, is a Senior Consultant at the Free Market Foundation. He has written extensively on the legality of state action and the meaning of statutes.

Disclaimer: The articles and videos expressed in this publication are those of the authors. They do not purport to reflect the opinions or views of Green Building Africa, our staff or our advertisers. The designations employed in this publication and the presentation of material therein do not imply the expression of any opinion whatsoever on the part Green Building Africa concerning the legal status of any country, area or territory or of its authorities.

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.