25 projects upgrading existing transformers in South Africa to ‘unleash about 13GW into the grid’ – Electricity Minister

Google+ Pinterest LinkedIn Tumblr +
  • Projects are underway to upgrade Eskom’s infrastructure in the areas of generation and transmission in effort to increase their capacity and resolve load shedding.

Addressing a media briefing on Sunday, Minister of Electricity, Dr Kgosientsho Ramokgopa, said 25 projects to upgrade the existing transformers and increase their capacity are currently in construction. He did not specifically  identify the projects, their capacity or locations.

“We are talking about 25 projects that can unleash about 13 gigawatts of electricity into the grid. The work starts now to be connected by 2026 to ensure there is additional capacity. We need to ensure we expedite the projects and bring them quicker online so we can expand the grid capacity.

“These are the twin challenges [generation and transmission]that we are facing at the moment and we must resolve to address load shedding. Of course, the issue of distribution must receive attention,” the Minister said in Pretoria.

In addition, Eskom has identified 22 projects that can provide 24 gigawatts by 2033. The concentration of these projects is in the Western Cape, Northern Cape and Eastern Cape, as the coastal areas have the highest wind speed.

“From the Northern Cape, we can get about 5 845MW. In the Eastern Cape, we can get 5 875MW and 8 954MW in the Western Cape. Eskom will need R100 billion going into the 2025 financial year and by 2029, we will need about R170 billion. The Eskom balance sheet will not be sufficient to finance this. We need alternative sources of financing and that is the work we are doing,” the Minister said.

The minister did not mention that the IPP office under the Minister of Mineral Resources and Energy, Mr Gwede Mantashe, is the only ministry allowed in terms of the Electricity Act to procure new generation capacity. Mantashe has failed to deliver a single electron to the grid since taking office in 2019. Read more 

Eskom’s Group Executive, Transmission , Mr Segomoco Scheepers, joined the Minister of Electricity yesterday to give a progress update on the Transmission Grid expansion as well as reminding the nation why Eskom is unbundling and commenting on the National Transmission Company South Africa licence to operate. Image credit: Eskom

Last month at a meeting with transmission service providers (EPC’s), the Managing director of Eskoms’ new Transmission Company, Mr Segomoco Scheppers, said that the country needed to add more than 1500 km of new transmission lines annually over the next ten years. This is to ensure transmission capacity to accommodate more than 50 GW of new generation power which will mainly come from intermittent renewable energy (wind and solar projects).

Currently, Eskom’s transmission division is adding 300 km of new power lines annually. Scheppers confirmed that in the last ten years, only 4 347 km of new powerlines were added.

Another challenge is transformer capacity. Scheppers confirmed that more than 122 600 MVA transformation capacity would have to be added, representing 77% of Eskom’s current installed base of just over 160 000 MVA. In the last ten years, only 19 060 MVA has been added to the grid infrastructure.

Scheepers joined the Minister of Electricity yesterday to give a progress update on the Transmission Grid expansion as well as reminding the nation why Eskom is unbundling and commenting on the National Transmission Company South Africa licence to operate which was awarded by the country’s energy regulator last week. Read more

Grid capacity

Ramokgopa also gave an update on the Energy Availability Factor for the week 24 July – 28 July 2023.

“During this week in question, we had a peak on 25 July, where we had capacity available to the tune of 29 376MW. This energy availability is the sum of a number of elements, which include planned outages. On Friday (28 July), we had the highest of that period with 4 126MW. That represents 1 600MW above what we had projected for our planned outages for the winter period. When the planned outages are up, it means that we are doing everything that is possible in an orchestrated fashion to ensure we are able maintain the units and when they return, hopefully they will be more resilient and overtime, it will improve the capacity available,” the Minister said.

Ramokgopa said the albatross remains the capacity loss factor, where units fail as a result of a multiplicity of factors.

“The principle reason… is boiler tube leaks. They are a big contributor to the failure rate. In the context of the winter outlook, the best case scenario was that the unplanned loss capability factor would be about 15 000MW and the worst case scenario was that it would be about 18 000MW.

“We are just shy of 16 000 MW. It is an area that is receiving our attention. The partial load losses simply means that the units are producing but not at the desired level. This is at 6 340MW. We want to improve their efficiency so that they are able to perform better and give us a significant number of MW,” the Minister said.

Eskom is working on reducing the unplanned capability loss factor (UCLF). We want to improve the performance of the units by reducing the partial load losses. When you bring those together, they add to the available capacity. Those are the areas that we are tracking,” he said.

Ramokgopa assured citizens that Eskom is working hard ensure the country does not go beyond Stage 4.

“On outage slips, this is one area that we are seeing significant improvement. It almost halved from 3 476 MW. We are at 1 843MW. This is a function of planning and management. It has received extended attention by various station managers. This is one area that I am confident that we will continue to see major strides going into the future,” the Minister said.

Author: Bryan Groenendaal

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.