Tanzania: Construction of 2115MW Julius Nyerere Hydro-Power Project on Track

  • The excavation works of three power water ways which will power nine turbines at the Julius Nyerere Hydro-Power Project in Tanzania, along the Rufiji River, has reached 74 percent completion according to the Project Manager, Eng. Said Kambanga.
  • The appointed construction contractors are a joint venture between Egyptian contractor, Elsewedy Electric and the Arab Contractors Company.  

Kambanga explained that the excavation of the Water Ways which will direct water to the powerhouse is an important stage in the project execution after the diversion of water from its ordinary route. He affirmed that the excavation works are set to be completed by December this year, stressing that there are no foreseen setbacks to hinder the process.

Kambanga also added that the construction of the Power House will be finalized around the same time that the tunneling works will be completed making way for the other stage of the project which is pouring concrete in both areas. This stage is expected to start in January 2021. Implementation of the entire project on track.

Rendering of Julius Nyerere Hydropower Station. Image credit: Elsewedy Electric

Related news: Construction of Tanzania’s 2115MW Rufiji River Hydro Project Begins

Eng. Said Kambanga confirmed that everything with regard to the implementation of the entire flagship project was going on as planned. He said that together with his fellow patriotic experts, have been working day and night to ensure the East African Country’s goals of possessing a state of the art hydropower production facility in the continent and the first of its kind in Sub-Saharan Africa is realized within the stipulated time.

Project Details and Scope of Works

Employer: Tanzanian Ministry of Energy
Contractors: JV Arab Contractors Company and Elsewedy Electric
Project location: Stigler’s Gorge Area, the dam is located in the Morogoro area on Rufiji River – Tanzania
Completion Period: 42 months including 6 months mobilization

Project Objectives:
Generating electricity with capacity of 2115MW to satisfy energy needs in Tanzania Control water flow in the period of flooding and thus providing the necessary water requirement

Main items:
-Total excavation is about 4 million m3
-Total aggregate backfilling is about 7.5 million m3
-Total volume of concrete is about 2.6 million m3
-Total weight of reinforced steel is about 64000 ton

Scope of Work:
-Main dam for storage of water to generate hydropower using RCC concrete for main dam with total length 1025m at crest level and 130m dam level
-Construction of 4 saddle dams for reservoir impounding of water with length of 1.4km, 7.9km, 4.6km and 2.6km with a maximum height 21.3m, 14m, 12.4m and 5.5m respectively, with a capacity to impound approximately 33 billion m3 of water
-Construction of a hydropower plant with a capacity of 2115mw and a substation of 400kv; in addition to 400kv transmission lines to the nearest point of the public network The civil works includes the following:
-Permanent access roads connecting the site with the existing roads network and length about 21km
-Temporary access roads that connect all permanent facilities with length of 59km
-Main dam of RCC on Rufiji River Power plant with administration building, control building, workshops and stores
-Connecting power station 400kv including transmission lines 4 variable height and length dams for water impounding of reservoir Diversion tunnel 660m length (15*17m) and 2 cofferdams
-The main spillway is located on the center of the main dam with 7 radial gates and an emergency spillway is located in the first saddle -Permanent concrete bridge on Rufiji River
-Integrated residential complex on an area of 19000m including housing and playground, permanent furnished offices; in addition to temporary residential complex, utilities, lighting, drinking water and water treatment

Main electromechanical works for power house:
-Power plant 2115 -9 vertical Francis turbines, each turbine capacity is 235mw
-9 butterfly valves for entrance
-9 vertical axis generators
-Water and sewage cooling systems
-Ventilation, air-conditioning, firefighting and communication systems
-Protection, control and monitoring equipment
-3 diesel generators for the power plant, dam and spillway

Upon completion, with a total electricity generation capacity of 2,115 megawatts, the project is expected to cut power tariffs which will lead to the reduction of the cost of living for Tanzanians as well as the production cost in industries.

Related news: AfDB approves USD150million for 50MW Malagarasi Hydro Project in Tanzania

Author: Bryan Groenendaal

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.