- Another extended deadline for South Africa’s Battery Energy Storage Independent Power Producer Procurement Programme (BESIPPPP) Bid Window 3 falls due on 28 November 2024.
- The deadline was initially extended from 31 July 2024 to 31 October 2024 which was requested from prospective bidders.
- They cited delays at Eskom where bidders have experienced delays in securing grid-access cost estimate letters (CEL’s) that are required for bid qualification which has also cause a submission deadline extension in BESIPPPP Bid Window 2.
The department launched a third Request for Proposal (RFP) under the Independent Power Producer Procurement Programme (IPPPP), calling for the procurement of 616 MW of new generation capacity from battery energy storage technologies for five storage facilities that are located within the Free State province on 28 March 2024.
Author: Bryan Groenendaal