South Africa: Redstone CSP Achieves First Debt Draw Down

  • The ZAR 11.6 billion Redstone concentrated solar power (CSP) project will provide power to 200,000 households upon completion. 
  • Commercial operation scheduled to start in Q4 2023.
  • The African Development Bank acted as the Mandated Lead Arranger and Coordinating Bank, committing ZAR 2.306 billion to the transaction.

South African Redstone concentrated solar power (CSP) project has achieved its first debt drawdown on the largest renewable energy investment in South Africa to date.

Related news: The four types of concentrated solar power explained

The African Development Bank (AfDB) acted as the Mandated Lead Arranger (MLA) and Coordinating Bank for the ZAR 11.6 bn total investment, with a commitment of ZAR 2.306 billion to the transaction. The project has also secured financing from leading international and South African financial institutions including ABSA Bank, CDC Group, Development Bank of Southern Africa (DBSA), Deutsche Investitions- und Entwicklungsgesellschaft (DEG), Nederlandse Financierings-Maatschappij voor Ontwikkelingslanden (FMO), Investec Bank, Nedbank Limited, Sanlam Limited, and the Industrial Development Corporation of South Africa.

Redstone is led by ACWA Power, a leading Saudi developer, investor and operator of power generation, water desalination and hydrogen plants in 12 countries, which is also the lead shareholder in Redstone with co-shareholders including the Central Energy Fund, Pele Green Energy and the local community.

Related news: Next generation solar concentrated power now under development 

Located in the Northern Cape Province of South Africa, the Redstone project will be equipped with a 12-hour thermal storage system that will deliver clean and reliable electricity to nearly 200,000 households round the clock. The construction for the project is well underway and is currently in its ninth month of construction. The engineering works for the project is over 58% completed, whereas procurement and construction works stand at over 45% and 6% respectively.

A key construction milestone, tower foundation for the project has been completed with the commencement of operations scheduled for Q4 2023. Through the successful mobilization of international project finance, Redstone has facilitated approximately ZAR 7 billion in foreign direct investment to fund and support the strategic energy transition goals of the country.

Redstone CSP will offset an estimated 440 metric tons of CO2 emissions per year while also providing value-adding ancillary services to Eskom, and it is the first renewable energy project to offer ancillary services in the country. The project is certified under the Climate Bonds Standard and Certification Scheme and aligned with the goals of the Paris Climate Agreement which seeks to limit global warming to under 2 degrees Celsius.

In addition to efficiently delivering clean energy to the national grid, the Redstone project will offer tangible socioeconomic value through utilizing local supply chains and creating job opportunities: the project will reach close to 44% local content on procurement during the construction period; create more than 2,000 construction jobs at peak, with about 400 from the local community; and create approximately 100 permanent direct jobs during the operating period.

Author: Bryan Groenendaal

Source: AfDB

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.