Norway to Supply UK with Hydro and Wind Power via New 720km Subsea Cable

  • The UK and Norway are now able to share renewable energy for the first time following the commissioning of the world’s longest subsea electricity interconnector.
  • National Grid’s €1.6 billion North Sea Link (NSL), a joint venture with Norwegian system operator Statnett, will start commercial operations today, marking a major milestone in the UK’s journey to net zero.
  • By enabling the trade of renewable energy between the two countries, North Sea Link will help reduce the burning of fossil fuels in the UK and avoid 23 million tonnes of carbon emissions by 2030.

The 720km cable, which connects Blyth in Northumberland with the Norwegian village of Kvilldal, near Stavanger, will start with a maximum capacity of 700 megawatts (MW) and gradually increase to the link’s full capacity of 1400MW over a three-month period. The gradual increase in capacity follows the Norwegian system operator’s standard approach for integrating new interconnectors. Once at full capacity, NSL will provide enough clean electricity to power 1.4 million homes.

North Sea Link will be the fifth interconnector for National Grid, which also operates links to Belgium, France and the Netherlands. By 2030, 90% of electricity imported via National Grid’s interconnectors will be from zero carbon sources saving 100 million tonnes of carbon – equivalent to taking two million cars off the road.

NSL has taken six years to build. Laying of the undersea cables began in 2018 and more than four million working hours have been spent on the project, including 5,880 working days at sea.

Norwegian power generation is sourced from hydropower plants connected to large reservoirs, which can respond faster to fluctuations in demand compared to other major generation technologies. However, as the water level in reservoirs is subject to weather conditions, production varies throughout seasons and years.

When wind generation is high and electricity demand low in Britain, NSL will enable renewable power to be exported from the UK, conserving water in Norway’s reservoirs. When demand is high in Britain and there is low wind generation, hydro power can be imported from Norway, helping to ensure secure, affordable and sustainable electricity supplies for UK consumers.

Author: Bryan Groenendaal

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.