Mozambique Will go to Tender for Construction of 1500MW Mpanda Nkuwa Hydroelectric Dam

  • The Mozambican government has announced  that it would launch international public tenders by June for contracting entities to carry out studies to construct the Mpanda Nkuwa hydroelectric dam.

The director of the Mpanda Nkuwa Hydropower Project Implementation Office (Gmnk), Carlos Yum, said at a press conference held last Friday in Maputo, that the tender would select institutions to carry out environmental, market, hydrological, geotechnical and financial impact studies for the construction of the project.

Related news: Controversial 1500MW Mpanda Hydro Dam project moving ahead

Originally planned several years ago, the Mphanda Nkuwa project was relaunched by the President Nyusi in 2018, and would be the largest dam in Mozambique after Cahora Bassa. It will be located 60 kilometres downstream from Cahora Bassa on the Zambezi River in the interior of Mozambique, about 1,500 kilometres northwest of Maputo, the Mozambican capital.

“The studies are supposed to take between two and two and a half years to conduct, but we are trying to shorten them to a year to a year and a half,” Yum said.

Yum said that building the dam was expected to begin in 2024 and last at least seven years. “Mozambique wants to be the energy hub in southern Africa because it has natural resources for that,” he added. The infrastructure, he continued, is budgeted at between USD4.5 billion (€3.6 million) and USD5 billion (€4.1 billion) and will have the capacity to generate between 1300MW and 1500MW.

That amount of power will make Mpanda Nkuwa the second-largest hydroelectric dam in the country, after the Cahora Bassa Hydroelectric Dam (HCB), which generates 2070 MW. 

Author: Bryan Groenendaal

Source: LUSA

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.