Africa Energy Indaba
Africa Energy Indaba

Loadshedding remains suspended for 10 months in South Africa

Google+ Pinterest LinkedIn Tumblr +
  • Eskom reports that the focused execution of the Generation Recovery Plan continues to deliver the suspension of loadshedding for 303 consecutive days since 26 March last year. 

A further substantial milestone of 300 days without loadshedding was reached on Tuesday 21 January and 10 months without loadshedding will be achieved on Sunday 26 January, further demonstrating the progress in Eskom’s turnaround strategy.

Last August, Eskom shared its summer outlook for the period from 1 September 2024 to 31 March 2025, predicting a likely scenario of a loadshedding-free summer due to structural generation improvements. This outlook remains unchanged.

Key Performance Highlights: 

  • Average unplanned outages over the past week were 12 717MW, a 1 119MW improvement compared to the same period last year.
  • Year-to-date unplanned outages average 12 060MW, remaining below the summer base case of 13 000MW by 940MW.
  • As of today, unplanned outages stand at 11 772MW, while available generation capacity is 27 961MW, sufficient to meet tonight’s forecasted peak demand of 24 461MW.
  • The Unplanned Capacity Loss Factor (UCLF) is at 25.25% for the financial year-to-date (1 April 2024 to 23 January 2025), improving from 32.68% in the corresponding period last year. This represents a ~7.4% improvement.
  • The weekly EAF slightly improved from 57.0% at the beginning of the financial year to 59.58% from 20 January 2025 to 23 January 2025, while the year-to-date EAF is at 61.79%, a significant improvement of ~6.9% compared to the same period last year (54.9%).
  • Ongoing planned maintenance at 7 739MW aligns with our summer maintenance strategy to further improve reliability in preparation for winter 2025 and beyond.
  • Strategic use of peaking stations, including pumped storage and OCGTs, remains available to manage electricity demand during peak times, particularly during evening peaks (17:00 to 22:00).
  • Between 1 April 2024 and 23 January 2025, Eskom spent approximately R9.87 billion, which is below budget, generating 1 604.72GWh. This is significantly lower than the 4 185.65GWh generated during the same period last year.
  • The OCGT load factor for 1 April 2024 to 23 January 2025 stabilised at 6.57%, compared to last year’s figure of 17.14%.
  • The OCGT load factor for 17 to 23 January 2025 was 5.95%, higher than the 4.65% for the same period last year.

Author: Bryan Groenendaal

Source: Eskom

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.