Increased Project Capacity Threshold for Wind and Solar Projects in South Africa’s REIPPPP Bid Window 6

News Flash

The criteria states that each project must have a contracted capacity within the range specified below for each technology:

Onshore wind

  • 50MW Minimum Contracted Capacity
  • 240MW Maximum Contracted Capacity (previously 140MW)

Solar PV

  • 50MW Minimum Contracted Capacity
  • 240MW Maximum Contracted Capacity (previously 75MW)

Link to the full Bid Window 6 request for proposals summary document issued by the Department of Mineral Resources and Energy HERE.

The wndow seeks to procure a total capacity of 2600MW split between 1600MW for onshore wind and 1000MW for Solar PV.

Author: Bryan Groenendaal

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.