Eskom Implements Loadshedding Amid ‘Trips’ at Medupi, Kusile and Duvha Power Stations

News Flash

  • Eskom regrets to inform the public that due to a loss of ten generating units at seven power stations during the past 24 hours, Stage 2 loadshedding will be implemented starting at 17:00 this evening until 22:00 on Tuesday night.

Failure of three generation units at Tutuka was due to loss of air compressors, a unit at Majuba was forced shutdown while another unit tripped. A generation unit at Kriel was taken down for a boiler tube leak. A unit was forced down due to a steam leak at a unit at Matla power station, while trips at a unit each at Medupi, Kusile and the Duvha power stations are being investigated.

This represents a total loss of 6 044MW over this 24 hour period, bringing the total unplanned capacity lost to 16 118MW. Planned maintenance is 4 171MW.

Author: Bryan Groenendaal

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.